• Preparation of Progress Chart requirement with consolation of the Manager (Billing) and after finalization to be sent to head office.
• Reconciliation of materials.
• Preparation of IPC’s Bill.
• Calculating the quantity of constituent material from the drawing in advance of facilitate the purchasing of items.
• Generation of client Bill as per required formats.
• Preparation of RFI for IPC’s Bill.
• Verify the bill of quantities with actual work execution.
• Inspect the contract request for extra items and prepare rate analysis and variation items.
• Monitor rate of Progress.
• Maintain and update Payment Records.
• Preparation of Variation Order.
• Preparation of Abstract of BOQ Item Quantity.
• Preparation of strip chart.
• Preparation of DPR & QPR.
• Preparation of Monthly Progress Report & Mail Head Office.
• Preparation of Key Plan.
• Checking of structure as per drawing, making daily, weekly & monthly progress report, Preparing and checking bar bending schedule (BBS), estimate quantities, RA Bill and coordination with other staff, client & contractor for timely compaction of project.
• Measurement of works and entering in the Measurement book.
• Level checking & Entry in level book.
• Site Work knowledge of Building, Bridge, Road and Railway.
• Auto CAD worked on highways drawing, architecture drawing, Drawing L-Section X-Section Railway Drawing Highway & Roads etc.